[ARCHIVED] Route 1 Paving update

MassDOT has contracted with Brox Industries for the repaving of Route 1 in Ipswich.  Milling work is scheduled to start on 8/11/19 at night and is anticipated to take approx. 4 weeks to complete.  Following the milling work Brox will be adjusting manhole and catch basin structures for 1-2 weeks following the milling work.  The paving work is scheduled to begin in mid to late Septmeber and will also take approx. 4 weeks to complete.  