Brox started the installation of the binder course of asphalt on Tuesday November 10, 2015. Work will stop for Veteran's Day and will commence on Thursday November 12, 2015 at 7 am. Due to delays with the work Brox will be completing the binder paving work on Friday November 13, 2015. On Monday November 16, 2015 Brox will be raising all of the gate boxes, manholes covers and catch basin grates to the final paving elevation. Final top course paving is scheduled to begin on Tuesday November 17, 2015 and is scheduled to take two days to complete.