Starting Friday, May 20th, at 7 AM, the Town's contractor, Nocella Paving, will begin preparing for pavement reclamation at 7 AM on Drumlin Road and then onto Payne Street and Poplar Street (County Street to Turkey Shore Road) in the afternoon.
On Monday, May 23rd, reclamation will continue on Payne and Poplar and move to Drumlin. On Tuesday, May 24th, reclamation on Fairview will begin at 7 AM. Binder paving on Drumlin Road will begin on Wednesday at 7 AM and then move to Payne and Poplar and then to Fairview. Paving will take approximately two days to complete and should be completed by the end of Thursday, May 26th. If you have any questions or comments, please email them to dpw@ipswichma.gov.