The Town has contracted with Brox Industries for the repaving of a portion of Brown Sq, Brewery Pl, South Village Green, Old Essex Rd, Northgate Rd from Essex Rd to Old Essex Rd, Linebrook Rd from Pillowlace Ln to Boxford Rd, Boxford Rd from Linebrook Rd to approximately the Hood Pond Landing, and Town Farm Rd from Fowler's Ln to Greens Point Rd. Work is scheduled to start on Brown Square Monday May 8, 2017. The current order in which the streets will be done are:
- Brown Square
- South Village Green
- North Gate
- Old Essex Rd
- Linebrook Rd
- Boxford Rd
- Town Farm Rd
This order is subject to change and all work is weather dependent any inclement weather will delay the scheduled work.